A copy of the tentative timeline for construction of the new
facility is below. Discussion is ongoing
with the architects and the project manager.
|
Activity
|
Duration
|
Start
|
Finish
|
|
Drawings to PC for approval
|
1
|
|
May 10
|
|
Special PC meeting
|
1
|
May 22
|
|
|
(Special PC meeting)
|
1
|
|
May 29
|
|
Contract Drawings Complete
|
1
|
|
May 31
|
|
Drawings out to bid
|
1
|
|
June 3
|
|
Advertise Project
|
1
|
|
June 5
|
|
Advertise Project
|
1
|
|
June 12
|
|
Advertise Project
|
1
|
|
June 19
|
|
Last Addendum
|
1
|
|
June 21
|
|
Bids to Treasurer – opening
1:00 PM
|
1
|
|
June 27
|
|
Recommend to board for
approval
|
1
|
|
July 8
|
|
Notice to Proceed
|
1
|
|
July 10
|
|
Mobilization
|
5
|
July 15
|
July 19
|
|
Install Temporary Fence
|
4
|
July 22
|
July 25
|
|
Install Silt Fence
|
4
|
July 26
|
July 31
|
|
Temporary Road and Lay Down
Area
|
10
|
July 22
|
Aug 2
|
|
Temporary Power (trailors)
|
5
|
July 22
|
July 26
|
|
Material Procurement (site
structures)
|
35
|
July 22
|
Sep 6
|
|
Material Procurement (rebar
for footers)
|
24
|
July 22
|
Aug 23
|
|
Prepare site for footers
|
30
|
July 22
|
Aug 23
|
|
Dig and pour footers
|
25
|
Aug 23
|
Sep 27
|
|
Site Utilities (water)
|
5
|
Sept 9
|
Sept 13
|
|
Site Utilities (storm)
|
20
|
Sept 16
|
Oct 11
|
|
Site Utilities (sanitary)
|
5
|
Oct 7
|
Oct 11
|
|
Underground Electric
|
5
|
Oct 7
|
Oct 11
|
|
Masonry to grade
|
25
|
Sept 9
|
Oct 11
|
|
Gym Masonry
|
30
|
Sept 23
|
Nov 11
|
|
Underground MEP
|
30
|
Sept 16
|
Oct 25
|
|
Slab on Grade
|
40
|
Sept 30
|
Nov 15
|
|
Community Space High Walls
|
20
|
Nov 4
|
Nov 29
|
|
Kitchen Penthouse High
Walls (1st story)
|
15
|
Dec 2
|
Dec 20
|
|
Pour Penthouse Floor
|
10
|
Dec 27
|
Jan 10
|
|
Kitchen Penthouse High
Walls (1st story)
|
15
|
Jan 13
|
Jan 31
|
|
Set bar joists and deck at
high walls
|
25
|
Feb 3
|
Mar 7
|
|
Roofing at high walls
|
30
|
Mar 10
|
Apr 18
|